- Home
- Departments
- Public Works
- Construction Reports
- 50th Street Storm Sewer Project
50th Street Storm Sewer Project
Project Overview
The Village has experienced multiple high-intensity rain events that exceeded the limited capacity of the Village's sewer system resulting in flooded basements, overland flooding in a number of depressional areas and private property drainage issues south of 47th Street. In response to the increasing frequency and intensity of rain events, the Village Board requested staff to pursue funding and engineering solutions that reduce flooding. View more information on flooding south of 47th Street.
The 50th Street Storm Sewer project seeks to reduce the incidences of overland flooding within the drainage basin south of 47th Street. The scope of work for the project includes constructing a dedicated storm sewer on 50th Street and associated lateral sewer segments that will drain stormwater from existing depressional areas.
The Village completed the engineering for the 50th Street Storm Sewer project in 2016 and went out to bid in the Spring of 2016. The project was stopped and delayed from its original schedule due to the litigation with the adjacent quarry, Lehigh Hanson. In 2018 the Village reached an agreement with Lehigh Hanson that settles the issues raised in a lawsuit that had been pending for two years. The agreement will allow the Village to move forward with its planned stormwater relief project when other elements of the overall project are in place.
The settlement includes funds for the construction of a stormwater pipe on the east side of East Avenue around the west and north perimeters of the quarry. That perimeter pipe will accept the stormwater through the 50th Street project and thus divert stormwater from discharging into the quarry. Meanwhile, the Metropolitan Water Reclamation District (MWRD) is studying the feasibility of constructing a detention facility on property adjacent to the northeast corner of the quarry. That detention facility, if constructed, would receive the stormwater that will flow from the 50th Street project and through the perimeter pipe. When fully completed the Village's 50th Street project is anticipated to provide flood relief to the drainage basin south of 47th Street.
Anticipated Schedule
The anticipated schedule for the project is as follows:
Action | Completion |
---|---|
Preliminary engineering analysis for MWRD detention facility | April, 2019 |
Project scope refinement, meeting with stakeholders, agreement development and execution [Village, MWRD, IDOT] | August, 2019 |
Detailed engineering and permitting for detention facility | February, 2021 |
Detailed engineering and permitting for north route pipe | August, 2020 |
Detailed engineering and permitting for 50th Street Storm Sewer | February, 2020 |
Construction of detention facility | March, 2025 |
Construction of north route pipe | March, 2024 |
Construction of 50th Street Storm Sewer | March, 2026 |
Construction Notices
Please select the following links for construction notices that have been issued for this project.
Project Updates
Please select the following links for notices that have been issued for this project.
- Announcement - Stormwater Management Project Update - July 13, 2016 (PDF)
- Announcement - Stormwater Management Project Update - August 18,2016 (PDF)
- Announcement - Stormwater Management Project Update - September 19, 2016 (PDF)
- Announcement - Stormwater Management Project Update - November 4, 2016 (PDF)
- Announcement - Stormwater Management Project Update - November 14, 2016 (PDF)
- Announcement - Stormwater Management Project Update - November 28, 2016 (PDF)
- Announcement - Stormwater Management Project Update - December 21, 2016 (PDF)
- Announcement - Stormwater Management Project Update - June 23, 2017 (PDF)
- Announcement - Stormwater Management Project Update - March 7, 2018 (PDF)
- Announcement - Stormwater Management Project Update - March 31, 2018 (PDF)
- Announcement - Village and Hanson Material Service Reach Settlement Agreement - December 19, 2018 (PDF)